Question 1: fit a full task into a window
A fictional review must run for 45 uninterrupted minutes in a room available from 10:10 to 11 a.m. No setup or buffer is required. What is the latest start time that fits?
Answer and explanation
10:15 a.m. Subtract 45 minutes from the 11 a.m. latest finish. The room is already available then because its window starts at 10:10. Starting at 10:20 would end at 11:05 and violate availability. The five unused minutes before 10:15 do not shorten the required review.
Question 2: include a required reset
A fictional demonstration starts at 1:35 p.m. and lasts 40 minutes. The room then needs a 15-minute reset. A second 30-minute demonstration begins as soon as permitted. When does it end?
Answer and explanation
The first ends at 2:15, the reset ends at 2:30, and the second ends at 3 p.m. Total elapsed time is 40 + 15 + 30 = 85 minutes from 1:35. Omitting the reset gives 2:45, which violates the stated condition. Keep preparation and changeover periods visible on the timeline.
Question 3: wait for every prerequisite
Two fictional tasks begin at 9 a.m. with separate workers. Data Check takes 50 minutes, and Layout takes 35. Final Review takes 20 minutes and requires both tasks to be complete. There is no changeover gap. What is the earliest Final Review finish?
Answer and explanation
10:10 a.m. Data Check ends at 9:50 and Layout at 9:35. Final Review must wait until 9:50, then takes 20 minutes. Adding all task times would ignore permitted parallel work. Beginning review at 9:35 would ignore the longer prerequisite.
Question 4: test one shared resource
Two fictional appointments each need the same interviewer for 25 minutes. The interviewer is available 2–3 p.m. A ten-minute gap is required between appointments, but no gap is needed before the first or after the second. Can both fit?
Answer and explanation
Yes, exactly. The required span is 25 + 10 + 25 = 60 minutes. One valid arrangement is 2–2:25, a gap until 2:35, then 2:35–3. Adding an extra ten-minute gap after the second would invent a requirement. Omitting the middle gap would also violate the rule.
Question 5: apply an inclusive finish boundary
A fictional task lasts 35 minutes and must finish no later than noon. It may start at 11:25. Does that start satisfy the deadline?
Answer and explanation
Yes. It finishes at exactly noon, which is allowed by “no later than noon.” A requirement to finish before noon would be stricter, but that is not the wording supplied. Evaluate equality explicitly instead of assuming a deadline always excludes its stated time.
Question 6: find the missing condition
A fictional meeting lasts 30 minutes and may start between 9 and 11 a.m. The problem gives no room availability or participant restrictions. Does it establish a unique start time?
Answer and explanation
No. Multiple starts satisfy the stated window. Duration does not choose one start within it. A question requesting a unique appointment would need another condition or objective. Do not invent a preference for earliest available, a particular room or a participant's schedule.
Question 7: count the defined days
For a fictional exercise, working days are Monday through Friday with no holidays. A task received Thursday must finish by the end of the second working day after receipt. The receipt day is excluded. Which day is the deadline?
Answer and explanation
Monday. Friday is the first working day after Thursday, and Monday is the second. Saturday and Sunday are excluded by the definition. Counting Thursday itself would give Friday and contradict the explicit exclusion. This is a supplied mathematical rule, not a statement of a real agency's deadline policy.
Question 8: demonstrate an earliest-finish bound
Three fictional tasks of 15, 20 and 25 minutes use one worker, cannot overlap and require no gaps. All are available at 10 a.m. No order restrictions apply. What is the earliest all can finish?
Answer and explanation
11 a.m. Their total required work is 60 minutes, and one worker cannot perform it in parallel. Starting at 10 with no gaps achieves that lower bound. The order is not unique, but the earliest finish is fixed under the supplied conditions. A different order cannot reduce the sum when no additional constraints or gaps apply.
Review the constraint you missed
Classify errors as time arithmetic, omitted buffer, incomplete dependency, shared-resource conflict, wrong boundary or invented uniqueness. Rebuild the timeline with the exact violated rule highlighted. Then solve a fresh case that changes one duration or resource condition.
Use logical reasoning practice for pure ordering and following instructions for conditional rules. Introduce assessment-specific timing only after the method works on unfamiliar examples, and keep personal practice results separate from official selection outcomes.
Candidate questions
How do I check a scheduling answer?
Verify durations, start and finish windows, dependencies, shared resources and required gaps. Then check the requested objective. A schedule that satisfies one deadline can still violate another condition.
Should I assume tasks can overlap?
Use the supplied rules. Different resources may permit parallel work, while a single worker or room may prevent it. If a necessary resource condition is absent, do not silently invent it to force a unique answer.
Are these official civil service scheduling questions?
No. They are original PSP learning examples. OPM and POST describe reasoning abilities in specific assessments, but the actual hiring authority determines your examination's content, timing and scoring.
Does a valid schedule prove it is the earliest possible?
No. Feasibility shows that the constraints can be met. An earliest-finish claim also requires showing that the schedule cannot finish sooner under the supplied conditions. Answer the exact task rather than treating every valid arrangement as optimal.
Official sources
- OPM common Occupational Reasoning assessment description
- California POST dispatcher applicant FAQs: ordering actions
Verified November 21, 2026. The current agency bulletin and your individual assessment instructions control.